2006-07
Seek development permit (February 2006).
Decant existing programs and services and commence Phase 1 renovations (June/July 2006).
2007-08
Complete Phase 1 renovations.
Relocate existing services from temporary decanting facilities to the newly renovated facility.
Complete Phase 2 planning.
2008-09
Begin Phase 2a construction (pending completion of new courthouse).
2009-10
Complete Phase 2a construction.
Phase 2b: Consolidate of present programs at Rocky Mountain Plaza/decanted facilities to permanent locations.